Not my house this time. A homeowner who also engaged Jishang Furniture reached out after reading my Jishang Furniture review and shared what her renovation was like. With her permission I'm writing it up as it goes. Her place is a resale HDB; mine was an EC — different homes, different challenges. I put these case studies up so we can learn from one another, take what applies, and hopefully have a smoother reno.
Short version: she is selling her current HDB and moving into a resale HDB, and she must hand the old flat to the buyer on 30 Nov 2026. China carpentry can save you a lot of money, but the timeline doesn't work like the usual local carpentry made in Malaysia. When you have a handover date, that difference matters a lot. As of 22 Nov 2026, the carpentry is in her flat. Jishang Furniture's owner sent it to the 3PF on 10 Nov 2026. It appears to have shipped around 12 Nov 2026, reached Singapore 21 Nov 2026, and last-mile ran on overtime 22 Nov 2026 for $850. From 3PF handoff to delivery was about 12 days. Install is planned for 23 Nov 2026 — not done yet. She still has a temporary stay arranged for the 30 Nov 2026 handover.
The situation: a fixed handover date
Once you sell your HDB, the buyer has a completion date and you need to be out. Can you move somewhere temporary? Can, lah. Rent short-term, stay with parents, put things in storage. But it's a hassle and extra cost, and most people want to avoid it. So the target becomes: new place ready to live in, roughly when the old place goes. Her date is 30 Nov 2026 — and she had told Jishang Furniture upfront that she wanted to move in then.
She had an ID handling the renovation, and Jishang Furniture was doing the carpentry. Sounds covered, right? The catch is that Jishang Furniture's own scope is the 3D design, agreeing the render and materials, then manufacturing. Measurement and installation are done by partners Jishang Furniture works with. Jishang Furniture gives a rough guide for how long their part takes. Renovation isn't only carpentry. Tiling, plumbing, electrical and painting all have to fit around it, and someone has to manage the whole sequence.
What pushed her timeline back
1. Kitchen tiles had to be finished before measurement
The kitchen tiles were finished on 5 Oct 2026, and only then was the site ready for measurement. That makes sense: measure before the tiles are done and the cabinets won't fit. The carpentry clock for a final site measure can't start until the wet works are finished.
2. Measurement took two visits
She was ready on 5 Oct 2026. A partner Jishang Furniture works with came to measure on 8 Oct 2026, but his equipment ran out of battery, so he could not finish. He came back on 12 Oct 2026 and finished the measurement.
To be fair: Jishang Furniture doesn't do the measuring itself. Jishang Furniture's own scope is the 3D design team producing the render, agreeing everything, then manufacturing the carpentry. Measurement and installation are done by partners Jishang Furniture works with. So this extra visit isn't strictly Jishang Furniture's own team.
Still, everything in a renovation is interlinked. A delay at the partner's measurement step still pushes back production, shipping, customs and install. That's why it sits on her timeline.
3. Drawing errors and unclear measurements
This is the one that actually dragged. The 3D render had already been approved on 30 Sept 2026 after three rounds, with materials confirmed the same day — before the final site measurement. After the measurement was finished on 12 Oct 2026, drawing errors and unclear measurements still had to be sorted. That was resolved on 17 Oct 2026. Piping was not really the issue for her. Older HDBs can have water pipes running through several areas, and that is worth planning for in general. It was not what pushed her dates back.
Her actual timeline
| Stage | Date | Days since previous step | Notes |
|---|---|---|---|
| First contacted Jishang Furniture | – | — | |
| Keys collected for resale HDB | 35 | — | |
| 3D render approved / materials confirmed | 6 | Render approved after 3 rounds; materials confirmed the same day | |
| Kitchen tiles finished — ready for measurement | 5 | — | |
| First measurement visit | 3 | Partner Jishang Furniture works with. Equipment ran out of battery; could not finish | |
| Measurement finished (2nd visit) | 4 | Same partner came back to finish. Not Jishang Furniture's own team | |
| Drawing errors and unclear measurements resolved | 5 | — | |
| Production started | 1 | Appears / as reported. Not a production-completion date. | |
| Sent to 3PF | 23 | Jishang Furniture's owner sent the carpentry to a third-party forwarder. Previously planned for 9 Nov. | |
| Shipped from China (sea) | 2 | Appears to have shipped around 12 Nov. I'm not 100% sure of this date. | |
| Arrived Singapore | 9 | — | |
| Customs cleared | — | – | No separate date given. Last-mile ran 22 Nov. |
| Delivered to her flat | 1 | Last-mile done on overtime. Delivered to her flat. Last-mile cost $850. About 12 days from 3PF handoff to delivery. | |
| Installed | Planned — not confirmed | 1 | Planned 23 Nov — not done yet. An installer she engaged separately. |
| Handed over current flat | Pending — update coming | Pending — update coming | Must still hand over 30 Nov 2026 — she will be out of the old flat |
| Moved in | Pending — update coming | Pending — update coming | Not expected by 30 Nov; temporary stay arranged |
For comparison, my own EC job is written up in the diary: Jishang Furniture sent the carpentry from Foshan, and the sea leg took about 12 days, followed by install day one and days 3 and 4. The full process is in the recent remodel story. I was racing a date too — a hard move-in for fengshui — but treat the diary as a reference, not a promise. On hers, 3PF handoff on 10 Nov 2026 to delivery on 22 Nov 2026 was also about 12 days — different legs, similar-looking number, don't treat it as a rule. As of 22 Nov 2026, the carpentry is in her flat, but install is only planned for 23 Nov 2026, and she still has to hand over the old flat on 30 Nov 2026. Temporary stay still arranged.
Where this stands now
As of 22 Nov 2026, the carpentry is in her flat. Jishang Furniture's owner sent it to a third-party forwarder on 10 Nov 2026. It appears to have shipped around 12 Nov 2026, reached Singapore on 21 Nov 2026, and last-mile ran on overtime on 22 Nov 2026 — $850. From 3PF handoff to delivery was about 12 days. Install is planned for 23 Nov 2026; she engaged an installer separately. Not done yet.
Last-mile into her HDB was $850, and it ran on overtime. On my EC job the last-mile van reload was $600 I didn't plan for — write-up here. Different building, different extra. Same lesson: the sea freight isn't the last number.
On 4 Nov 2026 she was already very unlikely to meet her 30 Nov 2026 handover-to-move-in target, and had made plans to stay elsewhere temporarily. Unfortunately not what she wanted. That fallback stay still stands. She had told Jishang Furniture upfront she wanted to move in on 30 Nov 2026.
With a few items wrong in the measurement, there has been some tension between her and Jishang Furniture. I should say this plainly: I am mostly hearing it from her side. I have not sat in on those conversations, so treat this as one account, not a verdict.
My own encounters: Jishang Furniture's owner didn't seem very open to criticism, in my experience. That is my personal impression, not a factual accusation, and it probably depends case by case. I wrote more about working with Jishang Furniture in the Jishang Furniture review.
Takeaway if you have a hard date: tell Jishang Furniture early — she did — then build in buffer, and plan a fallback stay anyway.
Why China carpentry timelines differ from Malaysia-made carpentry
With the usual local carpentry made in Malaysia, the factory is next door and delivery is short. With China carpentry like Jishang Furniture, every stage below is its own queue, and a delay in one pushes back everything after it:
- When measurement can take place. It depends on site readiness: tiles, hacking and plumbing positions need to be final first. In an old resale flat, add time for pipes in general — not because that was her delay, but because it does show up on some jobs.
- How long the 3D render takes — and whether it survives measurement. You need to review it properly and go back and forth until you're happy. Her render was approved after three rounds before the final site measurement; drawing errors still had to be fixed after. Rushing this to save time usually costs more later. Some of the terms that come up are in my Chinese carpenter glossary.
- Materials selection. Finishes, hardware (e.g. DTC vs Blum hinges), kitchen accessories like Higold. Each decision you sit on holds up production. She confirmed materials on 30 Sept 2026, the same day as the render.
- Overseas shipment, China to Singapore. Sea freight plus your forwarder. As of 22 Nov 2026, hers has already done that leg: sent to the 3PF 10 Nov 2026, appears to have shipped around 12 Nov 2026, reached Singapore 21 Nov 2026, last-mile into the flat 22 Nov 2026. I wrote about finding a 3PF and prepping before the carpentry arrived, and there's a Taobao 3PF helper on the site.
- Customs delays. Out of everyone's control, so leave buffer for it.
One more thing: measurement and installation are done by partners Jishang Furniture works with, and Jishang Furniture uses several install teams, so experience and speed can vary from job to job. Hers isn't automatically going to look like mine. For this job she engaged an installer separately.
What I'd tell anyone handing over their current place
- Start way earlier than you think. She first contacted Jishang Furniture on 20 Aug 2026, collected keys on 24 Sept 2026, and told Jishang Furniture upfront she wanted to move in on 30 Nov 2026. Talk to Jishang Furniture and your ID before you collect keys. Shortlist designs and materials so that after measurement it's only confirming, not deciding.
- Work backwards from the handover date. Write down when the carpentry must be installed, then the latest dates for shipping, render approval and measurement. If measurement can't happen until wet works finish, the wet works become your critical path. Then leave buffer for drawing fixes — she needed that after the measurement was finished — and for a measurement visit that cannot be completed in one go.
- Treat drawings as not final until after measurement. Her 3D render was approved before the final site measurement. Drawing errors and unclear measurements then took more time.
- Someone must own project management. An ID helps, but make sure they actually plan around the China carpentry lead time and don't treat it like local carpentry.
- Flag tricky site conditions upfront, including piping in older HDBs, so measurement doesn't drag. That was not her delay, but it is a common one.
- Budget for a Plan B. Tell Jishang Furniture your hard date early — she did — then still build in buffer, and plan a fallback stay. She has already arranged to stay elsewhere temporarily. Unfortunately not what she wanted.
- Sort out payments early. Paying RMB deposits and balances on time keeps production moving. See my MariBank SGD to RMB comparison.
If you're still deciding who to engage, my contractors list has the people I've used, and the measurements page is handy when you're checking drawings.
Her resale HDB and my EC bring different challenges. I write these case studies so we can learn from one another's jobs, take what applies to our own, and hopefully have a smoother reno. I'll update this after install. As of 4 Nov 2026 she was not expected to move in by 30 Nov 2026; as of 22 Nov 2026, the carpentry is in the flat but install is not done yet, and the 30 Nov 2026 handover still stands with a temporary stay.
FAQ
How long does China carpentry take to arrive in Singapore?
It depends on production and sea freight. On my own job, the sea leg after Jishang Furniture dispatched was about 12 days (details here). Measurement, render, materials and customs all come on top of that. In this homeowner's case, as of 4 Nov 2026 the carpentry had not been ready to send. As of 8 Nov 2026, it appears production started 18 Oct 2026 and the carpentry was ready to send to the 3PF, with handoff planned 9 Nov 2026 — that is not ocean shipping from China. As of 22 Nov 2026, it has been delivered to her flat: sent to the 3PF on 10 Nov 2026, appears to have shipped around 12 Nov 2026, reached Singapore 21 Nov 2026, last-mile 22 Nov 2026. From 3PF handoff to delivery was about 12 days. Install is planned 23 Nov 2026, not done yet, so I am still not giving a measurement-to-install total.
Can I measure for China carpentry before I collect keys to my resale HDB?
Usually you need access to the unit, and any tiling or plumbing changes need to be done first so the measurements are final. Measurement is done by a partner Jishang Furniture works with, not by Jishang Furniture's own team. Do the design shortlisting before keys, and measure as soon as the site allows. She first contacted Jishang Furniture on 20 Aug 2026, collected keys on 24 Sep, and kitchen tiles were finished on 5 Oct. The measurement partner first visited on 8 Oct but could not finish because his equipment ran out of battery; he came back on 12 Oct and finished.
Why does an old resale HDB take longer to measure?
Older flats can have water pipes running through several areas, and the carpentry has to work around them or leave access. That is worth allowing time for. In this homeowner's case, piping was not really the issue. The measurement partner first visited on 8 Oct but could not finish because his equipment ran out of battery, and came back on 12 Oct. After that, drawing errors and unclear measurements still had to be sorted.
Is China carpentry suitable if I have to hand over my current flat?
Can, but only if you plan early, leave buffer for shipping and customs, and have a fallback stay. If your timeline is very tight, compare it with local carpentry made in Malaysia, which skips the overseas leg. This homeowner told Jishang Furniture upfront she wanted to move in on 30 Nov 2026. As of 4 Nov she had already arranged a temporary stay. As of 8 Nov it appears production started 18 Oct and the carpentry was ready for the 3PF on 9 Nov, but sea shipping was still not confirmed. As of 22 Nov the carpentry has been delivered to her flat; install is planned 23 Nov and not done yet. She must still hand over the old flat on 30 Nov. Temporary stay still arranged.
Does Jishang Furniture's timeline cover the whole renovation?
No. Jishang Furniture's own scope is the 3D design team producing the render, agreeing everything, then manufacturing the carpentry. Measurement and installation are done by partners Jishang Furniture works with. Tiling, plumbing, electrical and painting are separate too, so someone needs to manage the full sequence.
Will my Jishang Furniture installation be the same as yours?
Not necessarily. Measurement and installation are done by partners Jishang Furniture works with, and Jishang Furniture uses several install teams, so experiences vary. My full write-up is in the Jishang Furniture review.