A lot of first-timers in Singapore default to an ID because the sequence feels like secret knowledge. Hacking? Flooring? Electrical? Carpentry? Nobody wants to be the person who laid vinyl too early or measured cabinets before the wall even exists.
I get it. I still skipped the ID. Not because I'm especially handy — I'm not — but because I was willing to ask the trades, one by one, what should come first. The longer write-up of this job is the recent remodel story. This post is just the order, so you can see the shape of it before you panic-hire someone to hold the calendar.
The sequence, in short
- Paperwork and the renovation permit. Contractor quotation, PE certification, floor plan, then iCondo. No site work until this is approved.
- Hacking, then clear the debris. First physical job. Mine took 2 days of hacking, then about 1–2 days to clear debris — roughly 4 days in total.
- The in-between trades. False ceiling and the kitchen wall from the contractor; gas piping from a team I sourced myself. Kitchen floor: about 5–6 tiles from Hup Kiong, contractor laid them. Electrical, plumbing, aircon shift. On my job these could go in more or less any order.
- Carpentry measurement — only after the new wall. The carpentry sits on that wall. Measure too early and the size is wrong. Plan power and light points before this too.
- Screed. A screeder levels the floor so vinyl can go down later.
- Painting. After the screed, and before vinyl.
- Vinyl. After painting, before carpentry.
- Carpentry last. Cabinets and the feature wall go in after the paint and the floor.
That's my EC. Your flat will differ — especially if you're not hacking walls, or you're in an HDB. The rest of this post is the notes behind each step, including what can overlap and what really cannot.
1. Paperwork before anyone lifts a hammer
EC / condo: contractor, PE, then iCondo
Before any work, I engaged a contractor — they gave a quotation listing the scopes — and a PE (professional engineer). I needed the PE because I was hacking walls. If you aren't hacking down walls, my understanding is a PE is probably not required.
Those documents had to exist before I could submit through iCondo, the estate's condo-management app, and apply for the renovation permit. The submission included the floor plan, the PE's certification, and the contractor's quotation. A renovation deposit of about $1,000 was placed on hold as part of the permit application.
There was a clarification with the management office, and after that the permit was approved quickly — just 1–2 days. Once it was approved, the estate blasted a notice to existing residents and pasted a notice near the lift area. That was the green light. Not before.

HDB, if I recall correctly
If I recall correctly, HDB flats also need some form of application or permit, and it is usually done by the contractor. I renovated an EC, so I'm not going to recite HDB rules from memory. HDB keeps the official write-up on applying for renovation approval.
2. Hacking is the first job
Once the permit is in, hacking comes first. How much depends on whether you're hacking down walls. Mine took only 2 days: two walls demolished, a TV feature wall, a wardrobe, and the entire set of kitchen cabinets. Clearing the debris took about another 1–2 days, so roughly 4 days in total for hacking plus clearing. I wouldn't put the next trades on top of a pile of rubble.

3. The in-between trades — order is flexible
Next came the false ceiling, building the new wall, plumbing, electrical, and shifting the gas piping. I also shifted the aircon units' positions — no new aircon installation, just moving what was already there. In my experience these can be done in more or less any order. I didn't treat that list as a sacred sequence. I treated it as a pile of jobs that all had to happen after hacking and before screed, painting, vinyl, and carpentry.
Not every trade has to come from the same contractor. Mine did the false ceiling and rebuilt the wall for the kitchen portion. The gas piping was shifted by a separate team I sourced myself. You can source some trades yourself.
Tiling on this job was only the kitchen floor — about 5–6 tiles replaced. I bought the replacement tiles from Hup Kiong, in the west of Singapore, and the contractor provided the labour. That sat with the wet works, before screed and vinyl in the rest of the house.


Electrical is the one I'd still plan carefully even if the calendar among those trades is loose. I scheduled it too early — that story sits in mistakes I'd avoid. Short version: plan every light point and power point before carpentry is measured or installed, and think about when the electrician should actually come in.
If you want a floor socket — under a desk, an island, that kind of thing — that's a before-screed decision, not an after-vinyl one. Moving a floor box later is messy.
4. Measure carpentry only after the new wall is up
This is the one I wish more first-timers heard before they booked a measuring date. If the cabinet sits on a wall you're still building, the measure waits. Same energy as the resale-HDB case study, where kitchen tiles had to be finished before measurement — different home, same idea: measure when the site is actually ready.
5. Screed
A screeding guy levelled the floor so vinyl could be laid. I didn't go hunting for a screeder on my own. The vinyl flooring person recommended him. If you're unsure who to call for screed, ask your flooring person. They usually already have someone.
6. Painting — after screed, before vinyl
Painting happened after the screed, and before the vinyl flooring. Then vinyl, then carpentry last.
7. Vinyl — before carpentry
Vinyl went in after the screed and the paint, after most of the hacking / wall / ceiling / plumbing / electrical / gas work, and before the carpentry. That order is why, later, I was buying floor protection while waiting for the cabinets — the vinyl was already down. I wrote that stretch up in getting ready for China carpentry to arrive.

8. Carpentry last
Carpentry was installed last. By then the messy work was done, the paint was on, the vinyl was down, and the new wall was there to measure against. Mine was China carpentry, so there was also a shipping and last-mile stretch in the middle — the goods landing, and an EC van-reload I hadn't planned for— then install day one and days 3 and 4. Sequence-wise, the point is the same even if your cabinets are local: they go in after the site can actually receive them.
The finished TV wall is in renovation complete. That missing LED light point on day one was the missed power point — the extra visit in mistakes I'd avoid. It wasn't obvious when the wall was still a drawing.

What can run at the same time, and what can't
Two different questions. One is order: which job has to finish before another can even start. The other is overlap: whether two trades can be in the unit on the same day.
What couldn't move on my job:
- No site work before the permit.
- Hacking (and clearing debris) before the next trades.
- Carpentry measurement only after the new wall was built.
- Kitchen floor tiling with the wet works, before screed and vinyl elsewhere.
- Screed, then painting, then vinyl, then carpentry last.
- Power points and light points planned before carpentry is measured or installed. The missed power point on my job was the LED driver light point — that is why Yongjin had to make an extra trip.
What was looser: false ceiling, the new wall, plumbing, electrical, shifting the gas piping, and shifting the aircon units. Those could shuffle. Some jobs can also run at the same time. I still wouldn't pack the unit.
My electrician warned that overcrowding can be an issue, so it's best to schedule trades on different days. Even when two jobs don't block each other on paper, they still need floor space, power, and a way to walk through the house. One trade at a time was calmer.
How I figured out the order without an ID
I didn't have the whole calendar mapped on day one. When I was unsure, I asked whichever trade was outstanding. Something like: I still have these jobs left, what should come first? They usually know. The screeder knew vinyl had to wait. The carpentry side knew the new wall had to exist. The electrician knew not to stack the unit with other crews. And you can source some trades yourself — I did that for the gas piping, instead of leaving it with the contractor who did the false ceiling and the kitchen wall.
That's the whole method. You don't need to pretend you're a project manager. You need to keep a list of what's left, and ask the next person on that list. If you want names of people I've actually used, they're on the contractors page — this post is about the order, not a recommendation list.
An ID can still make sense if you want someone to own design and chasing. I'm not anti-ID. I'm just saying the sequence itself is not a mystery. The trades already have it in their heads. You can ask.
Mistakes I'd avoid
I scheduled the electrician too early
This is the order mistake I actually made. I scheduled electrical too early, which meant 3 electrician visits in total. The missed power point was the LED driver light point on the TV wall — the same incident as install day one, when that wall couldn't finish because the point wasn't there. Yongjin Electrical was extremely accommodating — I highly recommend him — and made an urgent trip down to fix it so the carpentry progress wasn't held up.
Contact is on the Yongjin Electrical contractor page. I'm not repeating numbers here.
FAQ
What comes first in a Singapore renovation?
On my EC, nothing physical started until the renovation permit was approved. After that, hacking was the first job. Mine took 2 days — two walls demolished, a TV feature wall, a wardrobe, and the entire set of kitchen cabinets — then clearing the debris took about another 1–2 days, so roughly 4 days in total before the next trades could come in. Later it was screed, then painting, then vinyl, then carpentry last.
Do I need an interior designer to renovate in Singapore?
I didn't. I coordinated the trades myself on my EC. When I was unsure of the order, I asked whichever trade was still outstanding what should come first. They usually know.
Can I measure carpentry before the new wall is built?
Not in my case. The carpentry is installed on that new wall, so measurement could only happen after the wall was built. Measuring earlier would have been the wrong size. Plan power and light points before measurement too. I scheduled electrical too early, which meant 3 visits in total — the missed power point was the LED driver light point on the TV wall, the same incident as install day one.
How does the EC or condo renovation permit process work in Singapore?
Before any work, I engaged a contractor for a quotation listing the scopes, and a PE (professional engineer). I needed the PE because I was hacking walls. My understanding is a PE is probably not required if you aren't hacking down walls. The iCondo submission — the estate's condo-management app — needed the floor plan, the PE's certification, and the contractor's quotation. A renovation deposit of about $1,000 was placed on hold as part of the permit application. After a clarification with the management office, the permit was approved in just 1–2 days. Once approved, the estate blasted a notice to residents and pasted one near the lift.
Can renovation trades work on the same day?
Some jobs can run at the same time, but my electrician warned that overcrowding can be an issue. I found it better to schedule trades on different days.
Do HDB flats need a renovation permit too?
If I recall correctly, HDB flats also need some form of application or permit, and it is usually done by the contractor. I renovated an EC, so treat that as a recollection, not a rule.